In Berislav, Kherson region for the first time built a solar power station with a capacity of 7.68 MW, with the name “Taganskaya-2”.
According to the “Tauride news”, solar power plant, which is now working on the dumps on the North-East of Berislav, built by the Association of companies “Rentehno”. She was commissioned in the 20’s of January.

According to the specialist: “the Plant is designed with stringbag inverters and polycrystalline silicon elements. The inverter is assembled into complexes that are connected to special transformers, combined substations 0,4/10 kV. All the equipment produced by Ukrainian and foreign experts.”
Solar power plant “Taganskaya-2” will produce approximately 10942 MW-h of energy per year.
The General Director of industrial Association of companies “Rentehno” Eugene LACNIC noted that this SPP – the first such project with a full amount of work done. “Alternative energy is an advanced field of activity, especially if to take to attention an by 2030 “green” tariff. The terms full cost recovery of the plant should be about five years,” added the CEO.
A six-month construction of the power plant cost about $ 9 million dollars. During this time, about hundreds of borislavtsi and residents of nearby settlements were provided with jobs.

This project is an example for many Ukrainian cities and villages. Repeatedly, the network appeared information about the construction of any useful for the country of production at the site of the former dump. Be it solar power or a trout farm, the prospect of turning landfills on the territory of Ukraine in production on a national scale is growing every year and promises our country a bright future.